How to Project Cash Flow 90 Days Out

#Dashboards&Reporting#Dashboards&Reporting#Xero
How to Project Cash Flow 90 Days Out
AUTHORFelipe Chaparro
DATE25 NOV 2026
READ TIME10 MIN

How to project cash flow 90 days out: a 13-week forecast you can build in a spreadsheet, a worked example, and what to do when a week dips too low.

Every January, your bank balance drops faster than it should. Sites close for Christmas, stage claims stop, and the subcontractor and supplier invoices for December's work arrive anyway.

Here's how to project cash flow 90 days out with a 13-week forecast: what goes in, how to build it in an afternoon, and what to do when a week dips too low, with an example from a builder heading into the shutdown.

The short answer

To project cash flow 90 days out, list the next 13 weeks in a spreadsheet, start with today's bank balance, and put each payment in and out in the week the cash will actually move. Then find your lowest week. If it's below the floor you need, you have weeks, not days, to fix it.

Why 13 weeks

Thirteen weeks is far enough ahead to act on a gap, with time to bring a claim forward, agree supplier timing or arrange an overdraft. It's also close enough that most of the numbers are known: the claims you've scheduled, wages, rent and tax. And it covers a full quarter, so every regular payment shows up at least once.

What goes in

A forecast is two lists, cash in and cash out, with each amount in the week the money actually moves, not the week it's invoiced or due. If you're not sure why that gap matters so much, our post on why a growing business has no cash explains it.

Cash in:

  • Claims you've already sent, in the week the client usually pays. As a yardstick, businesses that invoice through Xero, with sales under $50 million, were paid 6.9 days after the due date on average in the September 2026 quarter (Xero's figures), so use each client's own record where you have it.
  • Claims you'll send, in the week you expect to reach each stage, allowing for any inspection or sign-off the contract needs, plus the days that client usually takes to pay. Use one row for each project, so you can see which build carries the gap.
  • Anything else, such as a deposit on a new contract or a variation the client has approved in writing.

Put claims in at the full amount the client pays, including GST: a $220,000 claim includes $20,000 of GST, which goes out again with your BAS. If a contract holds back a retention, forecast only what you'll receive, and the retention in the week it's due back, as the example below does in week 12.

Cash out:

  • Subcontractors and suppliers, in your payment-run weeks, for the work they'll have invoiced by then.
  • Wages and super, on each payday. Since 1 July 2026, super has to reach each employee's fund within 7 business days after payday (ATO), so it goes in the same week as the wages.
  • Tax: the tax withheld from wages, which goes each month once it's more than $25,000 a year, and the GST in the week your BAS is due. If you keep a separate tax account, show the transfers into it instead.
  • Overheads: rent, vehicles, insurance, software and loan repayments, on their dates.

How to build it in an afternoon

Your bookkeeper can do most of this from your accounting software in an afternoon. In Xero, the Aged Receivables Summary lists the claims you've sent, the Aged Payables Summary lists the bills you owe, and the pay calendar gives the pay runs; MYOB and QuickBooks have their own versions. You add the claims you expect, because you know when each stage will really be reached.

  1. 01Set up 13 columns, one for each week, starting next Monday, and put today's bank balance at the top of week 1.
  2. 02Add the claims you've sent, each in the week you expect the money, based on how that client has paid before.
  3. 03Add the claims you'll send, in the week each stage should be reached, plus the client's usual time to pay. Be honest about the shutdown.
  4. 04Add the fixed costs: wages and super on each payday, rent and loan repayments on their dates, and overheads each week.
  5. 05Add the supplier and subcontractor runs, for the work you expect to be invoiced by each run.
  6. 06Add the tax: the tax withheld each month and the BAS in the week it's due.
  7. 07Work out each week's closing balance: last week's balance, plus cash in, minus cash out. The lowest week is the one that matters.

Check your accounting plan first, because it may forecast for you. Xero's Comprehensive plan, at $107 a month, includes a 90-day cash flow forecast, and its Ultimate plans, from $143, a 180-day one (Xero). QuickBooks Online has a cash flow planner on every plan from Simple Start, at $35.99 (QuickBooks). MYOB's pricing page lists cash flow reports and graphs, but not a forecast. These are monthly list prices after any introductory offer, checked 7 November 2026, and Xero's include GST. Either way, the inputs are the same.

An example: the Christmas shutdown

Here's an example forecast for a builder like yours, built in the last week of November. The numbers are made up, but the pattern is a familiar one: sites close for three weeks over Christmas, in weeks 4 to 6, claims stop, and the bills for December's work arrive in January.

The first three weeks look like this in the spreadsheet, with one row for each kind of payment:

In the spreadsheetWeek 1Week 2Week 3
Opening balance$360,000$162,000$370,000
Stage claims paid$0$220,000$180,000
Subcontractor and supplier runs$140,000$0$150,000
Wages, after tax withheld$40,000$0$40,000
Super$6,000$0$6,000
Overheads$12,000$12,000$12,000
Closing balance$162,000$370,000$342,000

Each pay run is $50,000 before tax: $40,000 goes to your team, $6,000 of super goes to their funds, and the $10,000 of tax withheld goes to the ATO with the next monthly payment, so $20,000 leaves in weeks 4, 8 and 12.

All 13 weeks, in total:

WeekCash inCash outClosing balance
1$0$198,000$162,000
2$220,000$12,000$370,000
3$180,000$208,000$342,000
4$0$32,000$310,000
5$0$58,000$252,000
6$150,000$172,000$230,000
7$0$58,000$172,000
8$0$32,000$140,000
9$0$58,000$82,000
10$0$132,000−$50,000
11$240,000$58,000$132,000
12$30,000$32,000$130,000
13$190,000$278,000$42,000

Claims stop during the shutdown, apart from one December claim of $150,000 that the client pays late, in week 6, and no stage is reached again until week 11. The only retention due back in these 13 weeks, $30,000 on a home finished last year, arrives in week 12. In week 10, the first supplier run after the restart, $120,000, lands before the first claim of the year, and the balance goes about $50,000 below zero. In week 13, the BAS of $70,000 lands with a supplier run and a pay run. It covers October to December, so much of it is GST on claims from before this forecast starts, which is why you can't work it out from the table: ask your bookkeeper for the figure.

The floor is the lowest balance you're comfortable with. As a minimum, use your next pay run and its super, here $46,000. With five builds and supplier runs of $120,000 to $160,000, we'd suggest a safer floor for a builder: one supplier run plus a pay run, about $200,000. By that measure, week 1 is already tight, and every week from week 7 is too low.

So this isn't one bad week in February. From week 7, the balance stays under the floor: about $250,000 short of it in week 10, and still $158,000 short at the end of week 13. Across the 13 weeks, $318,000 more goes out than comes in, because the shutdown stops the claims while the bills for December's work and the BAS still arrive. Fixing week 10 alone would leave the business short again in March.

Built in the last week of November, the forecast shows all of this two months ahead, which is time enough to act. Size the fix to the worst week, about $250,000: some from a claim or deposit brought forward to before Christmas, some from spreading the restart supplier runs, and the rest from an overdraft or line of credit arranged now. The next section takes each step in turn.

A bar chart of an example builder's closing bank balance for each of 13 weeks, starting with $360,000 in the bank. It peaks at $370,000 in week 2, stays above a $200,000 floor through the shutdown in weeks 4 to 6, then falls under it from week 7 and goes about $50,000 below zero in week 10. It recovers to $132,000 in week 11, holds about $130,000 in week 12 and ends week 13 at about $42,000.
A 13-week forecast over the Christmas shutdown

What to do when a week dips too low

What you can do depends on how far away the gap is. The further ahead you see it, the more options you have, and the cheaper they are.

Six weeks or more away

  • Bring cash forward: ask whether a stage can be reached and claimed earlier, or whether a deposit on a new contract can land before the gap.
  • Agree timing with your biggest suppliers for the restart runs, now rather than in February.
  • Arrange an overdraft or a line of credit while the forecast still shows how you'll repay it. Banks lend more easily before a gap than during one, so take the forecast with you.

Three to five weeks away

  • Chase every overdue claim by phone, and send each claim the day the stage is reached. Automatic reminders help, and our post on automating overdue invoice emails shows how to set them up.
  • Delay spending that can wait, such as new equipment or a vehicle.

Under three weeks away

  • Pay wages, super and tax first, before any other bill.
  • Call any supplier you can't pay in full before the due date, with a date you can keep.
  • If the BAS falls in a week you can't cover, still lodge it by the due date, then set up a payment plan with the ATO. The ATO charges interest on what's unpaid until it's cleared, so the shorter the plan, the less it costs.
Three steps, by how far away the gap is. Six weeks or more: bring a claim forward, agree timing with suppliers, and arrange an overdraft. Three to five weeks: chase overdue claims by phone, send each claim on the day, and delay spending that can wait. Under three weeks: pay wages, super and tax first, call suppliers before the due date, and lodge the BAS on time.
What to do, by how far away the gap is

Keep it current: 15 minutes every Monday

A forecast is only useful while it's current. Every Monday, replace last week's estimates with what actually happened, move any claims that slipped, and add a new week 13 at the end. Your bookkeeper can update the numbers, and you or your project managers confirm the claim dates, because you know when each stage will really be reached.

If updating it by hand gets old, the figures can come straight from your accounting software into a dashboard. That's part of our Dashboards & Reporting service.

Start this week: open a spreadsheet, put in your bank balance and the next 13 weeks of claims and bills, and find your lowest week. If you'd like a second pair of eyes, book a 15-minute call with our team in Sydney, by phone or video. Bring your claim schedule and your supplier terms, and we'll look over your first forecast with you, so you leave knowing your lowest week and the first thing to do about it. There's no obligation after the call, and we don't upsell.

SEE HOW WE FIX THIS

See the exact system we build to fix this

Build my cash flow dashboard
Felipe Chaparro

WRITTEN BY

Felipe Chaparro

Systems Architect and Founder of SYSBILT. Felipe engineers custom automation, AI workflows, and performance web architectures for scaling Australian service businesses.

/ READY?

Want to talk about this

Book a free call and we'll walk you through how this applies to your business

BOOK A CALL
NOW ACCEPTING PROJECTS