Why are your profit margins shrinking? The five places project margin leaks, a worked example, and how to track margin on every project, every week.
IN THIS ARTICLE
Your practice is busier than last year. There are more projects on the board, the team is flat out, and the fees look healthy. But at the end of the quarter, you've kept less of each fee than you used to, and nobody can say which projects did it.
If you're asking why your profit margins are shrinking, the answer is usually in a handful of projects, not across the whole practice. Here's where the margin goes, how to see it project by project, and what to change first.
The short answer
Project margins usually shrink in five places: extra work you don't bill, time nobody records against the project, subconsultant costs you don't pass on, discounts, and overheads that creep up. Your profit and loss report shows the total, not which projects lost money, so track the margin on each project and review it every week.
Why your profit and loss report can't show it
Your profit and loss report adds up every fee and every cost for the month. It tells you the practice made less, but not that the Smith garden ran 36 hours over or that an arborist's report never made it onto an invoice. By the time the quarter's numbers arrive, you've priced more projects on the same assumptions.
To find the leaks, you need the margin on each project: the fee, less the cost of the hours and anything else the project used. If the report shows a profit but the bank balance keeps falling, that's a different problem, about timing rather than margin, and our post on why a growing business has no cash covers it.
An example: one fixed-fee project
Here's the Smith garden as a made-up example: a design project with a fixed fee of $28,000, before GST. An hour of the team's time costs $100, and the section on tracking margin, further down, shows how to work that out.
- Planned: 140 hours, so $14,000 of time and a margin of $14,000, or 50% of the fee.
- What happened: two extra design rounds and three extra site visits added 36 hours. At 176 hours, the time cost $17,600, and the margin fell to $10,400, or 37%.
- One more cost: a $1,200 arborist's report the fee didn't cover took the margin to $9,200, or 33%.
Nothing went wrong that anyone would call a disaster. Of the $14,000 margin planned, $4,800, about a third, went in small, reasonable-looking steps, and none of them showed up on the month's report.

The five places margin leaks
01Work beyond the scope
Extra design rounds, a changed brief and "while you're at it" requests get absorbed as goodwill. The fix is a written scope that says how many design rounds and site visits the fee includes, and a short variation note, agreed before the work, for anything beyond it.
02Time nobody records against the project
Admin, travel, site visits and rework happen, and if they're not recorded against the project that caused them, its margin looks better than it is. Ask everyone to record their time against a project every day, including the hours you can't bill, so you can see what each project really used.
03Subconsultant and supplier costs you don't pass on
Arborists, engineers, surveyors and printing all cost more than they did, and a fee set from last year's estimate quietly absorbs the difference. Check current prices before you send a fee proposal, and say in the proposal which costs you'll pass on, and with what margin.
04Discounts to win the work
Taking 10% off a fee feels small, but the work costs the same, so the whole discount comes off your margin. On the Smith garden, 10% off is $2,800, a fifth of the planned $14,000 margin. On work with a thinner margin it's worse. If a $100 fee costs $85 to deliver, the profit is $15. Take 10% off, and the fee is $90, the cost is still $85, and the profit is $5: two-thirds of it gone. Mark discounted projects in your project list, so the Monday review shows whether they end up below plan, and when a client pushes on price, offer less scope rather than a lower fee. Our post on measuring your sales conversion rate shows how to tell whether discounts are winning you more work.
05Overheads that creep up
Software, insurance and rent rise a little every year, and so does the cost of employing people: super went up to 12% of earnings on 1 July 2025 (ATO). If your hourly rates and fee estimates still use last year's cost of an hour, every project starts with a thinner margin than you think.

How to track margin on each project
For each project, you need three numbers: the fee, the hours times the true cost of an hour, and the subconsultant and supplier costs. The fee less the other two is the project's margin. Count everything you billed, variations included, and everything you paid, including costs you passed on. Overheads are already in the cost of an hour, so don't add them again. That makes this margin closer to a net margin than a gross one, so don't compare it with gross margin figures, which leave overheads out. If your fees are split into stages, such as concept design, development application and documentation, track each stage as its own line, so you can see which one runs over.
Work out the true cost of an hour
The quickest way is from last year's profit and loss report: add up salaries, super and overheads, leaving out subconsultants and other costs you pass on, and divide by the hours the team spent on client projects. One average cost of an hour is enough to start. If a principal's pay doesn't show in that report as a market salary, for example because they take drawings, add what you'd pay someone else to do the role first. Otherwise the quick way gives a lower cost than the one-person method below.
To see it for one person, divide what they cost you in a year by the hours they can bill. Here's a made-up example for one designer:
- Salary: $90,000, plus 12% super of $10,800, so $100,800.
- Their share of overheads, such as rent, software and insurance: $29,200, so $130,000 in total.
- Billable hours: about 1,300 a year, once leave, public holidays and non-billable time come out.
- True cost of an hour: $130,000 divided by 1,300, or $100.
The 1,300 is this example's figure, not a benchmark. A full-time year at 38 hours a week is about 1,980 hours, and after four weeks' annual leave and about 10 public holidays, about 1,750 are left (Fair Work). Billing 1,300 of them is about three-quarters. That share is called utilisation: the lower it is, the more each billable hour costs. Work out your own from your timesheets: the hours each person billed, divided by the hours they were paid for after leave.
For a part-timer, use their own salary and billable hours. For a principal, use what you'd pay someone else to do the role, not what you draw, so every project carries the real cost of your time.
If your time records are patchy
You can start with rough numbers: they're enough to show the worst leaks.
- For recent projects, estimate the hours from calendars, site-visit records and the number of design rounds. The projects that ran well over will still stand out.
- For the next two weeks, ask everyone to record a daily total for each project, in half-hour blocks, including the hours they can't bill.
- Tell the team why: the records are there to price the next proposal properly, not to check on anyone.
Where to record it
Ask your bookkeeper whether your accounting plan already tracks projects. If it doesn't, these plans do. The prices are each company's monthly list price on its Australian pricing page, after any introductory offer, checked 7 November 2026. Xero's include GST, and MYOB's and QuickBooks' pages don't say.
- Xero: the Ultimate plans, from $143, with 10 project users and $7 for each extra one (Xero).
- MYOB: Business Pro, at $70, tracks each project's profit and loss (MYOB calls projects jobs), and AccountRight Plus, at $165, adds a budget for each one (MYOB).
- QuickBooks: Plus, at $89.99 for 5 users, or Advanced, at $138 for 25 users (QuickBooks).
Practice management tools for design practices do it too. Whichever you use, your bookkeeper sets up the projects, the team records time against them, and you hold the review. The tool matters less than the habit: every hour and every cost recorded against the project it belongs to.
The 15-minute weekly review
Every Monday, list the projects that closed last week and the big ones still running, with each one's planned margin and its margin now, sorted by the gap, biggest first. If your fees aren't built from planned hours yet, use the margin you aim for on every project as the plan, and plan the hours on your next proposal. Here's what that might look like, as a made-up example:
| Project | Planned margin | Margin now | Gap | What to look at |
|---|---|---|---|---|
| Smith garden | 50% | 33% | 17 points below | Extra design rounds and site visits, and a report the fee didn't cover |
| School playground | 45% | 38% | 7 points below | Site visits beyond the scope |
| Townhouse courtyards | 50% | 47% | 3 points below | On track |
| Council park upgrade | 40% | 39% | 1 point below | On track |
| Rooftop terrace | 50% | 52% | 2 points above | On track |
Here, two projects are more than five points below plan, so they're this week's conversations: what the Smith garden tells you about pricing the next garden, and a variation note before any more site visits on the school playground. Over a few weeks, patterns appear. If the same type of project keeps coming top, it's a pricing problem. If different projects appear but the cause is always extra hours, it's a scoping or estimating problem.
Start this week
- 01Pick five recent projects and work out the actual margin on each: the fee, less the hours at the true cost of an hour, less the other costs. If the hours weren't recorded, estimate them as above: rough numbers are enough to start.
- 02Give every project a code, a number or short name used in the accounts and on timesheets, so every hour and cost is recorded against the project it belongs to.
- 03Hold the 15-minute review every Monday, and flag any project whose margin is more than five percentage points below plan.
If you do only one thing, do the first: five projects are enough to show where your margin goes.
We build dashboards that list every project's fee, hours, costs and margin against plan, updated from your accounting and time records, so the Monday review takes minutes, not an afternoon. That's part of our Dashboards & Reporting service.
If you'd like a second pair of eyes, book a 15-minute call with our team in Sydney, by phone or video. Bring the fee and your best estimate of the hours for three recent projects, and we'll work out their margins with you, so you leave knowing which leak to fix first. Rough numbers are fine. There's no obligation after the call, and we don't upsell.

WRITTEN BY
Felipe Chaparro
Systems Architect and Founder of SYSBILT. Felipe engineers custom automation, AI workflows, and performance web architectures for scaling Australian service businesses.



